JavaScript is Required
Accepted Projects Details
Showing Record(s) 1 to 15 of Total 275 Green Box -Projects where all Issues are resolved
S.No Project Name Ministry-Department Description Of Projects
(As furnished by the applicant)
Estimated Investment(in Crores)
1 TRANSMISSION SYSTEM ASSOCIATED WITH KISHENGANGA HEP  Power   Brief: The project is to implement transmission evacuation system associated with Kishanganga Hydro Electric Project (3x110 MW) being developed in the state of Jammu & Kashmir. Under the scheme, two transmission lines is being implemented. (i) 220 KV D/C Kishanganga-Amargarh line & (ii) 220 KV D/C Amargarh-Wagoora line. The first transmission line i.e. Kishanganga-Amargarh line need to be completed early to match with the commissioning of 1st unit of Kishenganga HEP. The sanction cost of project is 269 cr. The date of approval of January, 2015 and the scheduled commissioning of unit-I is July, 2017 and unit-II is March, 2018. The ROW/physical possession of land required for the project is at 398 locations (150 locations for unit-I and 248 locations for unit-II). Ministry of Power/Powergrid has already deposited Rs. 8.74 cr. towards land compensation. Forest clearance for the project has been accorded in March, 2017. All the packages under the transmission system have been awarded. Physical progress for unit-I is 35% and for unit-II is 17%. The financial progress is 40%. Completion of above transmission project is affected due to severe Right of Way (RoW) constraints arising out of delay in finalization of compensation for land, frequent local disturbances, unrest, arson and insurgency activities. The priority transmission line i.e. 220 kV D/c Kishanganga - Amargarh line is targeted for commissioning by Nov, 2017 provided ROW constraints are resolved and continuous support is extended by the State Govt. 269
2 1200 MW (2X600 MW) Phase-1, Anuppur Thermal Power Project of MB Power (Madhya Pradesh) Limited   Power   2x600 MW (Phase-1) Anuppur Thermal Power Project has been setup by MB Power (Madhya Pradesh) Limited. Both units achieved Commercial Operation. #Long Term PPAs for sale of around 70% power already signed with States of MP & UP. #FSA with SECL signed for 1200 MW capacity. #Open access for evacuation and transmission of power secured from CTU. #Water Agreement signed with the host state Govt. for meeting the water requirement of the Project. 8663
3 OGPTL - Odisha Generation Phase II Transmission Limited  Power   Various IPPs, expected to be commissioned in Odisha, had applied for grant of connectivity and LTOA/LTA. Seven IPPs were considered under phase I and transmission system for the same under implementation under HCTPC I scheme. Further following 5 projects were considered under Phase II generation projects in Odisha 1. Sterlite Energy Ltd (Ph I project) (LTA of 1000 MW under Ph II) 2400 MW 2. GMR Kamalanga Energy Ltd(Ph II) 350 MW 3. OPGC 1350 MW 4. Darlipalli(NTPC) 1600 MW 5. NSL Nagapatnam Power & Infratech 1320 MW and following transmission system has been finalized for evacuation of power from above mentioned generation projects (i) Immediate evacuation system for Ph II generation projects in Odisha • Sterlite TPP to Jharsuguda 400 kV D/C line • GMR to Angul 400 kV D/C line • OPGC to Jharsuguda 400 kV D/C line • Darlipalli to Jharsuguda 400 kV D/C line • NSL Nagapatnam to Angul 400 kV D/C line (ii) Common transmission system associated with Ph II generation projects in Odisha • Angul to Jharsuguda – Dharamjaygarh 765 kV D/C line(2nd) • Jharsuguda to Raipur pool 765 kV D/C line • LILO of Rourkela to Raigarh 400 kV D/C line(2nd) at Jharsuguda • Addition of 2x1500 MVA, 765/400 kV ICT at Jharsuguda • Addition of 2x1500 MVA, 765/400 kV ICT at Angul • Split bus arrangement at 400 kV and 765 kV bus in both Angul and Jharsuguda (iii) Out of the above transmission system, following scope of works is to be implemented through Tariff Based Competitive Bidding route is as follows Scope of transmission project 1. Jharsuguda to Raipur pool 765 kV D/C line 2. OPGC to Jharsuguda 400 kV D/C line 1223
4 Western Region Strengthening Scheme V, Transmission System for Connectivity of Essar Power Gujarat Limited and Transmission System associated with Solapur STPP (2x660MW) Part A.  Power   (i)WRSS-V: LILO of Lonikhand (MSEB) - Kalwa (MSEB) 400 kV S/C line at Navi Mumbai (16 Ckm) Sch. Completion : Sept., 2010 (Rev:Dec’16), Ant. Completion : Sept, 2017 (ii)System for connectivity of Essar Power 400 KV D/C Essar Bachau Line (452 Ckm) Sch. Completion Oct., 2013 (Rev:Mar’16), Act. Completion March, 2017 (iii)Transmission System to evacuate power from Solapur STPP towards Solapur (PG) for onward transmission to Southern Region.Sch. Completion : March, 2017, Ant. Completion : May, 2017 1335
5 Transmission System associated with Gadarwara STPS (2x800 MW) – Part-B.  Power   POWERGRID Parli Transmission Limited (PPTL), a 100% wholly owned subsidiary of Power Grid Corporation of India Ltd. [a CPSU under M/o Power] has been incorporated on acquisition through Tariff Based Competitive Bidding (TBCB) process to act as Transmission Service Provider (TSP) with a purpose to establish Transmission System for evacuation of power from Gadarwara STPS (2x800 MW) of NTPC (Part-B) and to dispatch to the beneficiaries State viz. MP, Maharashtra, Chattisgarh, Gujarat, Goa, Daman & Diu and Dadra & Nagar Haveli. Under the scheme, PPTL is to implement following i)Warora (Pooling Station) – Parli (New) 765 kV D/c line [349 Km] ii)Parli (New) - Solapur 765 kV D/c line [118 Km] iii)Parli (New) – Parli (PG) 400 kV D/c (Quad) line [18 Km] & iv)Establishment of 2x1500 MVA, 765/400 kV Parli (New) S/Stn. The above Transmission System is scheduled to be completed by January, 2018. 2225
6 Transmission System Associated with Gadarwara STPS (2x800 MW) of NTPC (Part-A)  Power   POWERGRID Warora Transmission Limited (PWTL), a 100% wholly owned subsidiary of Power Grid Corporation of India Ltd. [a CPSU under M/o Power] has been incorporated on acquisition through Tariff Based Competitive Bidding (TBCB) process to act as Transmission Service Provider (TSP) with a purpose to establish Transmission System for evacuation of power from Gadarwara STPS (2x800 MW) of NTPC (Part A) and to dispatch to the beneficiaries States viz. Madhya Pradesh, Maharashtra, Chattisgarh, Gujarat, Goa, Daman & Diu and Dadra & Nagar Haveli. Under the scheme, PWTL is to implement following i) Gadarwara STPS Jabalpur Pool 765kv D/c line [102 Km] ii) Gadarwara STPS Warora 765 kV D/c line [319 Km] iii) LILO of both circuits of Wardha Parli (PG) 400 kV D/c (Quad) line at Warora Pooling Station [93 Km] iv) Establishment of 2x1500 MVA 765/400 kV (New Pooling Station within the jurisdiction/boundary of Warora) The above Transmission System is scheduled to be completed by November, 2017. 2525
7 Talcher Super Thermal Power Project Stage-I  Power   Coal based thermal power station at District Angul , Odisha 2697
8 OPGC Expansion project at Ib Thermal, Jharsuguda  Power   2 x 660 MW expansion project (Units 3 & 4) at Ib Thermal Power Station, Banharpali, Jharsuguda. 10000
9 800 MW PARBATI HYDRO ELECTRIC PROJECT - II  Power   This hydro electric project is situated in Kullu district of Himachal Pradesh state and at about 260 Km from Chandigarh. The nearest broad gauge is at Kiratpur, which is 190 Km away. It is a run-off-the-river project to tap hydro potential of lower reaches of River Parbati. The scheme is ‘inter basin transfer’ type. The water of river Parbati shall be carried through a tunnel across Garsa valley to Sainj valley where the Power House is being constructed for generating 800 MW power. Diverting and using discharge of various nallas falling along the head race tunnel (HRT) alignment further augments water input. The project requires construction of 84 m high Concrete Gravity dam, 31.5 km long HRT with 6 m diameter and Power House (4 * 200 MW). This is a PRAGATI projects reviewed in PRAGATI meeting 17 feb 2016 7818
10 BRBCL-Nabinagar TPP (4X250 MW)-JV  Power   Coal based thermal power project located at Block: Nabinagar District: Aurangabad, 7998
11 NPGC-Nabinagar STPS(3X660 MW)-JV  Power   Coal based thermal power project located at Block: Nabinagar District: Aurangabad 13624
12 Meja STPP (2X660 MW) - JV  Power   Coal based thermal power projects located at Village: Kohdar, Laltara (Tehsil: Meja) District: Allahabad 9750
13 Solapur STPP (2X660 MW)  Power   Coal based thermal power project located at Village: Fatatewadi & Ahirwadi,District: Solapur, 9395
14 Bongaigaon TPP (3X250 MW)  Power   Coal Based thermal power project located at Village Kumguri at Salakati, PO Salakati (P), Distt Kokrajhar (BTAD), Assam – 783369. 6749
15 Mouda STPP Stage-II (2x660MW)  Power   Coal Based Thermal Power Project located at Village: Lapka and Kumbhari of Mauda tehsil District: Nagpur 7921
next last
Go to Navigation